In 2024, interconnection queues shrank for the first time in years
Heads up! This post is packed with charts and visualizations that are easier to explore on a larger screen. Want to come back later? Tap below to send it to yourself:
In 2024, interconnection queues across the U.S. shrank — not because demand disappeared, but because the rules changed.
Many speculative projects were cleared out en masse this year, leaving behind a sharper, more committed pipeline.
Regional Capacity Changes (2023 → 2024)
The chart below compares 2023 vs. 2024 cumulative active capacity by technology type and planning region, comparing snapshots taken at the end of each year. It reflects only projects that remained active at the end of each year, excluding anything withdrawn, completed, or otherwise removed from the queue. Green bars indicate an increase from 2023 to 2024; red bars represent a decrease.
That sea of red? It's not what we're used to seeing.
For years, active queue volumes grew at a breakneck pace — fueled by a surge of solar, wind, and storage projects. But in 2024, that trend reversed. Offshore wind fell by over 50%, solar dropped nearly 12%, and hybrid storage declined by nearly 20%.
One notable outlier to this trend is gas. Across every power market, gas-fired projects increased their presence in the queues. This stands in sharp contrast to the broader decline and serves as a reminder that thermal capacity is still an increasingly significant portion of the evolving grid mix.
📊Get alerted about these trends in real time, not months later.
All Regions



Increase
Decrease
2023 value
2024 value
So what changed?
Most signs point to queue reform. Over the past 18 months, ISOs like PJM, MISO, and CAISO implemented new rules requiring higher deposits, stricter site control, and milestone-based study processes. On top of that, FERC Order 2023 — while not yet fully implemented — means that these changes are here to stay. The one major exception? ERCOT, which isn't subject to FERC rules and continues to operate under its own policies.
One notable exception to the contraction trend was MISO, which saw a significant increase in queued capacity across nearly every technology type. At first glance, this might seem to contradict the broader story — but it likely reflects a timing artifact, not a structural break.
MISO's queue was largely frozen in 2023 as it transitioned to a new interconnection process. When it reopened in early 2024, a wave of new applications entered — potentially representing deferred demand from developers waiting on clarity around the new rules. In this light, MISO's growth doesn't undermine the queue reform hypothesis — it just reflects how differently that transition played out across regions.
It's too early to tell if this is a lasting correction or a temporary reset — but 2024 marks a clear turning point in the evolution of interconnection queues.
While some of the recent decline in active queue capacity might be attributed to fewer new applications, that's not the whole story. In fact, 2024 saw a massive spike in project withdrawals. Among projects with reported withdrawal dates (which is only about half of all withdrawn projects), plus withdrawals from CAISO cluster 15[1], 296 GW of capacity was withdrawn from the queues last year — more than double the amount withdrawn in 2023, and by far the largest annual total in the dataset.
The number of individual projects withdrawn also surged, jumping 92% year-over-year. This points to a broader structural shift: queue reform processes are not just filtering future applicants — they're forcing existing projects out. The bottleneck isn't closing at the entrance; it's clearing out the middle.
Annual Queue Withdrawals
🔔Get alerted the moment a project you care about is withdrawn.
⚠️ Note: This data includes only projects that reported their withdrawal dates — approximately 50% of all withdrawn projects. Actual withdrawal volumes are likely approximately double this amount.



Queue Timelines (2023 → 2024)
How long does it take to get through the queue?
To answer that, we analyzed the time between a project's interconnection request and its eventual commercial operation date (COD). For each power market, we calculated the median and interquartile range (25th to 75th percentile) of queue-to-COD durations for projects that reached COD in a given year.
These charts reveal that typical development timelines remain stubbornly long — often 3 to 5 years — with wide variability depending on the market. Some regions like PJM and the Southeast show relatively consistent durations to 2023, while others like SPP display more volatility and longer median timelines. Nationally, there's no clear evidence yet that queue reform efforts have meaningfully shortened the path to COD.
Note: ERCOT and NYISO are excluded from this analysis due to insufficient historical data for meaningful timeline comparisons. Including ERCOT would likely decrease the median timeline.
Note: These figures likely undercount the total number of projects reaching COD each year, as some ISOs and RTOs do not consistently report actual commercial operation dates.
⏱️Monitor queue timelines as they evolve — not just once a year.
All Regions: Queue-to-COD Duration



Withdrawal Timelines (2023 → 2024)
What about the projects that didn't make it?
To better understand the other side of queue attrition, we looked at how long withdrawn projects had been sitting in the queue before exiting. For each power market, we measured the time between a project's interconnection request and its withdrawal, and calculated the median and interquartile range for projects withdrawn in a given year.
The picture that emerges is just as striking. In 2024, many withdrawn projects had been in the queue for 4 to 5 years — a meaningful amount of time for developers to invest before walking away. In markets like CAISO, the median project sat in the queue for over 5.5 years before withdrawing. PJM, Southeast, and MISO show slightly shorter timelines, but still hover around the 3–4 year mark.
Importantly, this analysis includes only the roughly 50% of withdrawn projects that report a withdrawal date. While incomplete, we believe the trend is representative; these aren't just speculative applications disappearing overnight. In many cases, they're projects that stuck it out for several years before ultimately exiting, likely due to delays, reform-driven barriers, or shifting market conditions.
📈Track queue attrition timelines across markets, in real time.
All Regions: Queue-to-Withdrawal Duration



So what's left in the queue with a signed agreement?
Next, we looked at the most concrete indicator of near-term buildout: projects with signed Generator Interconnection Agreements (GIAs). These are far from speculative — they've made it through the queue, cleared studies, and signed contracts. In other words, they're real.
We found that ERCOT currently leads all other markets with over 100 GW of active GIA-signed capacity — a striking number, and another reminder of how different ERCOT's trajectory has been from the rest of the country. CAISO, PJM, MISO, and the West each show solid volumes as well, suggesting that despite broader attrition, there's still a healthy pipeline of projects ready — or nearly ready — to move forward.
Together, these GIA-backed projects represent the best signal we have of what's actually coming online in the near term — and they cut through the noise of speculative early-stage growth and contraction.
It's easy to focus on the volatility in early-stage queue volumes, but these GIA-backed projects serve as a reality check: a meaningful buildout is still very much in motion.
GIA-Signed Capacity by Market (as of May 2025)

But looking at power markets only tells part of the story. Breaking down these same GIA-signed projects by generation type reveals the technology mix that's actually getting built. Solar dominates with 148 GW of active capacity, but what's particularly striking is the emergence of hybrid projects — solar-plus-storage and other combinations — which represent 70 GW of active capacity. Together with standalone battery storage at 67 GW and wind at 65 GW, these four categories account for nearly 90% of all active GIA-signed capacity.
The suspended category tells its own story. Hybrid projects lead with 11 GW temporarily on hold — more than any other technology type — suggesting these complex, multi-component projects face unique interconnection challenges. Solar has another 6 GW suspended, while gas-fired generation sits at just 27 GW active with minimal suspensions. The prevalence of hybrids in both active and suspended categories underscores how the grid's future isn't just renewable — it's increasingly about integrated systems that combine generation with storage.
GIA-Signed Capacity by Generation Type (as of May 2025)

Interconnection requests in list format
All transmission grid interconnection requests All distribution grid (DG) interconnection requestsInsights
Charts State of interconnection queues — January 2024In 2024, interconnection queues shrank for the first time in yearsAll blog postsOther energy & climate tools
Inflation Reduction Act Bill Text Viewer ToolClimate Tech Jobs Tracker (30,000+ jobs)Climate Tech Hiring Trends & ChartsRequests by power market
Requests by status
Requests by cluster
Interconnection queue requests by state
Interconnection queue requests by generation transmission owner
Interconnection requests by year
Requests in 2025Requests in 2024Requests in 2023Requests in 2022Requests in 2021Requests in 2020Requests in 2019Requests in 2018Requests in 2017Requests in 2016Requests in 2015Requests in 2014Requests in 2013Requests in 2012Requests in 2011Requests in 2010Requests in 2009Requests in 2008Requests in 2007Requests in 2006Requests in 2005Requests in 2004Requests in 2003Requests in 2002Requests in 2001Requests in 2000Requests in 1999Requests in 1998Requests in 1997Requests in 1996Requests in 1995© 2025 Interconnection.fyi. All rights reserved.
Get the Data