Interconnection.fyi
Tracking U.S. ISO & utility interconnection queues

In 2024, interconnection queues shrank for the first time in years

By Steven Zhang, and Chris Talley
June 1, 2025

In 2024, interconnection queues across the U.S. shrank — not because demand disappeared, but because the rules changed.

Many speculative projects were cleared out en masse this year, leaving behind a sharper, more committed pipeline.

Regional Capacity Changes (2023 → 2024)

The interconnection.fyi team went digging through our historical dataset to see how active queue volumes have shifted year-over-year — and for the first time in recent memory, they're shrinking.

The chart below compares 2023 vs. 2024 cumulative active capacity by technology type and planning region, comparing snapshots taken at the end of each year. It reflects only projects that remained active at the end of each year, excluding anything withdrawn, completed, or otherwise removed from the queue. Green bars indicate an increase from 2023 to 2024; red bars represent a decrease.

That sea of red? It's not what we're used to seeing.

For years, active queue volumes grew at a breakneck pace — fueled by a surge of solar, wind, and storage projects. But in 2024, that trend reversed. Offshore wind fell by over 50%, solar dropped nearly 12%, and hybrid storage declined by nearly 20%.

One notable outlier to this trend is gas. Across every power market, gas-fired projects increased their presence in the queues. This stands in sharp contrast to the broader decline and serves as a reminder that thermal capacity is still an increasingly significant portion of the evolving grid mix.

📊Get alerted about these trends in real time, not months later.

All Regions

Interconnection.fyi logo
Interconnection.fyi logo
Interconnection.fyi logo

Increase

Decrease

2023 value

2024 value


So what changed?

Most signs point to queue reform. Over the past 18 months, ISOs like PJM, MISO, and CAISO implemented new rules requiring higher deposits, stricter site control, and milestone-based study processes. On top of that, FERC Order 2023 — while not yet fully implemented — means that these changes are here to stay. The one major exception? ERCOT, which isn't subject to FERC rules and continues to operate under its own policies.

One notable exception to the contraction trend was MISO, which saw a significant increase in queued capacity across nearly every technology type. At first glance, this might seem to contradict the broader story — but it likely reflects a timing artifact, not a structural break.

MISO's queue was largely frozen in 2023 as it transitioned to a new interconnection process. When it reopened in early 2024, a wave of new applications entered — potentially representing deferred demand from developers waiting on clarity around the new rules. In this light, MISO's growth doesn't undermine the queue reform hypothesis — it just reflects how differently that transition played out across regions.

It's too early to tell if this is a lasting correction or a temporary reset — but 2024 marks a clear turning point in the evolution of interconnection queues.

While some of the recent decline in active queue capacity might be attributed to fewer new applications, that's not the whole story. In fact, 2024 saw a massive spike in project withdrawals. Among projects with reported withdrawal dates (which is only about half of all withdrawn projects), plus withdrawals from CAISO cluster 15[1], 296 GW of capacity was withdrawn from the queues last year — more than double the amount withdrawn in 2023, and by far the largest annual total in the dataset.

The number of individual projects withdrawn also surged, jumping 92% year-over-year. This points to a broader structural shift: queue reform processes are not just filtering future applicants — they're forcing existing projects out. The bottleneck isn't closing at the entrance; it's clearing out the middle.

Annual Queue Withdrawals

🔔Get alerted the moment a project you care about is withdrawn.

⚠️ Note: This data includes only projects that reported their withdrawal dates — approximately 50% of all withdrawn projects. Actual withdrawal volumes are likely approximately double this amount.

1We explicitly included CAISO Cluster 15 withdrawals from 2024 (289 projects, ~126 GW) due to their outsized impact, despite their lack of reported withdrawal dates. While this improves accuracy, the total is still an undercount, because many other withdrawn projects do not have published withdrawal dates, and are therefore not included in this chart.
Interconnection.fyi logo
Interconnection.fyi logo
Interconnection.fyi logo

Queue Timelines (2023 → 2024)

How long does it take to get through the queue?

To answer that, we analyzed the time between a project's interconnection request and its eventual commercial operation date (COD). For each power market, we calculated the median and interquartile range (25th to 75th percentile) of queue-to-COD durations for projects that reached COD in a given year.

These charts reveal that typical development timelines remain stubbornly long — often 3 to 5 years — with wide variability depending on the market. Some regions like PJM and the Southeast show relatively consistent durations to 2023, while others like SPP display more volatility and longer median timelines. Nationally, there's no clear evidence yet that queue reform efforts have meaningfully shortened the path to COD.

Note: ERCOT and NYISO are excluded from this analysis due to insufficient historical data for meaningful timeline comparisons. Including ERCOT would likely decrease the median timeline.

Note: These figures likely undercount the total number of projects reaching COD each year, as some ISOs and RTOs do not consistently report actual commercial operation dates.

⏱️Monitor queue timelines as they evolve — not just once a year.

All Regions: Queue-to-COD Duration

Interconnection.fyi logo
Interconnection.fyi logo
Interconnection.fyi logo

Withdrawal Timelines (2023 → 2024)

What about the projects that didn't make it?

To better understand the other side of queue attrition, we looked at how long withdrawn projects had been sitting in the queue before exiting. For each power market, we measured the time between a project's interconnection request and its withdrawal, and calculated the median and interquartile range for projects withdrawn in a given year.

The picture that emerges is just as striking. In 2024, many withdrawn projects had been in the queue for 4 to 5 years — a meaningful amount of time for developers to invest before walking away. In markets like CAISO, the median project sat in the queue for over 5.5 years before withdrawing. PJM, Southeast, and MISO show slightly shorter timelines, but still hover around the 3–4 year mark.

Importantly, this analysis includes only the roughly 50% of withdrawn projects that report a withdrawal date. While incomplete, we believe the trend is representative; these aren't just speculative applications disappearing overnight. In many cases, they're projects that stuck it out for several years before ultimately exiting, likely due to delays, reform-driven barriers, or shifting market conditions.

📈Track queue attrition timelines across markets, in real time.

All Regions: Queue-to-Withdrawal Duration

Interconnection.fyi logo
Interconnection.fyi logo
Interconnection.fyi logo

So what's left in the queue with a signed agreement?

Next, we looked at the most concrete indicator of near-term buildout: projects with signed Generator Interconnection Agreements (GIAs). These are far from speculative — they've made it through the queue, cleared studies, and signed contracts. In other words, they're real.

We found that ERCOT currently leads all other markets with over 100 GW of active GIA-signed capacity — a striking number, and another reminder of how different ERCOT's trajectory has been from the rest of the country. CAISO, PJM, MISO, and the West each show solid volumes as well, suggesting that despite broader attrition, there's still a healthy pipeline of projects ready — or nearly ready — to move forward.

Together, these GIA-backed projects represent the best signal we have of what's actually coming online in the near term — and they cut through the noise of speculative early-stage growth and contraction.

It's easy to focus on the volatility in early-stage queue volumes, but these GIA-backed projects serve as a reality check: a meaningful buildout is still very much in motion.

GIA-Signed Capacity by Market (as of May 2025)

Interconnection.fyi logo

But looking at power markets only tells part of the story. Breaking down these same GIA-signed projects by generation type reveals the technology mix that's actually getting built. Solar dominates with 148 GW of active capacity, but what's particularly striking is the emergence of hybrid projects — solar-plus-storage and other combinations — which represent 70 GW of active capacity. Together with standalone battery storage at 67 GW and wind at 65 GW, these four categories account for nearly 90% of all active GIA-signed capacity.

The suspended category tells its own story. Hybrid projects lead with 11 GW temporarily on hold — more than any other technology type — suggesting these complex, multi-component projects face unique interconnection challenges. Solar has another 6 GW suspended, while gas-fired generation sits at just 27 GW active with minimal suspensions. The prevalence of hybrids in both active and suspended categories underscores how the grid's future isn't just renewable — it's increasingly about integrated systems that combine generation with storage.

GIA-Signed Capacity by Generation Type (as of May 2025)

Interconnection.fyi logo
Interconnection.fyi
Tracking U.S. ISO & utility interconnection queues

Interconnection requests in list format

All transmission grid interconnection requests All distribution grid (DG) interconnection requests

Insights

Charts State of interconnection queues — January 2024In 2024, interconnection queues shrank for the first time in yearsAll blog posts

Other energy & climate tools

Inflation Reduction Act Bill Text Viewer ToolClimate Tech Jobs Tracker (30,000+ jobs)Climate Tech Hiring Trends & Charts

Interconnection queue requests by state

Interconnection queue requests by generation transmission owner

Alberta Electric System OperatorAllegheny PowerAlliant Energy EastAlliant Energy WestAmeren IllinoisAmeren MissouriAmerican Electric PowerAmerican Municipal PowerAmerican Transmission CompanyAmerican Transmission SystemsArizona Public ServiceArkansas Electric Cooperative CorporationAssociated Electric CooperativeAvista UtilitiesBaltimore Gas and ElectricBangor Hydro ElectricBasin Electric Power CooperativeBig Rivers Electric CorporationBlack Hills Cheyenne Light Fuel and Power TransmissionBlack Hills Colorado ElectricBlack Hills PowerBonneville Power AdministrationCedar Falls UtilitiesCentral Hudson Gas and ElectricCentral Maine PowerCentral Power Electric CooperativeChelan County Public Utility DistrictCity Utilities of Springfield MissouriCity Water, Light and PowerCity of Columbia, MissouriCity of Muscatine, IowaCleco HoldingsColorado River Storage Project TransmissionColorado Springs UtilitiesCommonwealth EdisonConsolidated EdisonConsumers EnergyCooperative EnergyCorn Belt Power CooperativeDCR TransmissionDairyland Power CooperativeDayton Power and LightDelmarva Power and LightDesertLinkDominion EnergyDominion Energy South CarolinaDuke EnergyDuke Energy CarolinasDuke Energy FloridaDuke Energy IndianaDuke Energy Ohio and KentuckyDuke Energy ProgressDuquesne Light CompanyEast Kentucky Power CooperativeEast River Electric Power CooperativeEast Texas Electric CooperativeEl Paso ElectricEmpire District Electric CompanyEntergyEntergy ArkansasEntergy LouisianaEntergy MississippiEntergy New OrleansEntergy TexasEssential PowerEvergyEvergy Missouri WestEversourceEwington Energy SystemsFirstEnergyFlorida Power and LightGeorgia TransmissionGrand River Dam AuthorityGrand River EnergyGrant County Public Utility DistrictGridLianceGridLiance WestGridUnityHenderson Municipal Power and LightHoosier EnergyHorizon West TransmissionISO New EnglandITC Great PlainsITC MidwestITC TransmissionIdaho Power CompanyImperial Irrigation DistrictIndependence Power and LightIndianapolis Power and LightJacksonville Electric AuthorityJersey Central Power and LightKACYKansas City Board of Public UtilitiesKansas City Power and LightKansas Power PoolLS PowerLS Power Grid New YorkLafayette Utilities SystemLea County Electric CooperativeLincoln Electric System
Long Island Power AuthorityLos Angeles Department of Water and PowerLouisville Gas and Electric and Kentucky Utilities EnergyLoveland Area Projects TransmissionLower Yellowstone Rural Electric CooperativeMadison Gas and ElectricMaine Public ServiceManitoba HydroMetropolitan Edison CompanyMichigan Electric Transmission CompanyMichigan Public Power AgencyMid-Kansas Electric CompanyMidAmerican EnergyMidcontinent Independent System OperatorMidwest EnergyMinnesota PowerMinnkota Power CooperativeMissouri River Energy ServicesMissouri Western Energy CorporationMontana-Dakota UtilitiesMunicipal Commission of BoonvilleNAEANV EnergyNational GridNavajo-CrystalNebraska Public Power DistrictNew York Power AuthorityNew York State Electric and GasNew York TranscoNextEra Energy TransmissionNextEra Energy Transmission SouthwestNorthWestern EnergyNortheast UtilitiesNorthern Indiana Public ServiceNorthern States Power CompanyNorthwest Iowa Power CooperativeNorthwestern Wisconsin Electric CompanyOhio Valley Electric CorporationOklahoma Gas and ElectricOld Dominion Electric CooperativeOmaha Public Power DistrictOrange and RocklandOrlando Utilities CommissionOtter Tail Power CompanyPECO Energy CompanyPJMPPL CorporationPacifiCorpPacific Gas and Electric CompanyPennsylvania Electric CompanyPlatte River Power AuthorityPortland General ElectricPotomac Electric Power CompanyPrairie PowerPublic Service Company Of ColoradoPublic Service Company of New MexicoPublic Service Electric and GasPuget Sound EnergyRochester Gas and ElectricRochester Public UtilitiesRockland Electric CompanySacramento Municipal Utility DistrictSalt River ProjectSan Diego Gas and ElectricSantee CooperSeminole Electric CooperativeSouth Mississippi Electric Power AssociationSouthern California EdisonSouthern CompanySouthern Illinois Power CooperativeSouthern Indiana Gas and Electric CompanySouthern Maryland Electric CooperativeSouthern Minnesota Municipal Power AgencySouthwestern Power AdministrationSouthwestern Public Service CompanySunflower Electric Power CorporationTacoma Public UtilitiesTampa Electric CompanyTennessee Valley AuthorityTransource MissouriTri-State Generation and Transmission AssociationTucson Electric PowerUnited Gas Improvement CompanyUnited Illuminating CompanyUpper Peninsula Power CompanyValley Electric AssociationVillage of ArcadeVillage of IlionWAPA Sierra NevadaWAPA/BEPC/HCPD Integrated SystemWabash Valley Power AssociationWestar EnergyWestern Area Power AdministrationWestern Area Power Administration Desert Southwest RegionWestern Farmers Electric CooperativeWisconsin Electric Power CompanyWisconsin Public Service CorporationWolverine Power Supply CooperativeXcel Energy

© 2025 Interconnection.fyi. All rights reserved.

Get the Data