MISO Cluster: DPP-2016-AUG West
Total Projects: 35
Active Projects: 2
Active Projects per county
Capacity by Generation Type
Active Projects
Operational Projects
| Queue ID | Status | Capacity (MW) |
|---|---|---|
J302 | Operational | 101.2 |
J503 | Operational | 98.8 |
J512 | Operational | 250 |
J541 | Operational | 400 |
J555 | Operational | 140 |
J583 | Operational | 200 |
J587 | Operational | 200 |
J590 | Operational | 90 |
J611 | Operational | 110 |
J614 | Operational | 66 |
Withdrawn Projects
| Queue ID | Status | Capacity (MW) |
|---|---|---|
J414 | Withdrawn | 120 |
J415 | Withdrawn | 200 |
J439 | Withdrawn | 500 |
J457 | Withdrawn | 150 |
J459 | Withdrawn | 200 |
J511 | Withdrawn | 200 |
J562 | Withdrawn | 119.6 |
J563 | Withdrawn | 150 |
J575 | Withdrawn | 100 |
J577 | Withdrawn | 100 |
J593 | Withdrawn | 224 |
J594 | Withdrawn | 300 |
J596 | Withdrawn | 100 |
J597 | Withdrawn | 300 |
J598 | Withdrawn | 300 |
J599 | Withdrawn | 200 |
J607 | Withdrawn | 150 |
J613 | Withdrawn | 100 |
J615 | Withdrawn | 70 |
J637 | Withdrawn | 98 |
J638 | Withdrawn | 204 |
J650 | Withdrawn | 151.8 |
J651 | Withdrawn | 151.8 |
Stay up to date via our email newsletter:
Interconnection queue requests/projects in list format
All transmission grid interconnection queue requests/projects All distribution grid (DG) interconnection queue requests/projects Data center projects by state EIA860 planned and operational power plant projectsInsights
Charts State of interconnection queues — January 2024In 2024, interconnection queues shrank for the first time in yearsAll insightsGridTracker
GridTracker — the full interconnection data platformAbout GridTrackerQueue requests/projects by country
Queue requests/projects by power market
Queue requests/projects by status
Queue requests/projects by cluster
Queue requests/projects by U.S. state
Queue requests/projects by Canadian province
Data Centers
All data center projectsBy U.S. State
Interconnection queue requests/projects by transmission owner
Interconnection queue requests/projects by year
Queue requests/projects in 2026Queue requests/projects in 2025Queue requests/projects in 2024Queue requests/projects in 2023Queue requests/projects in 2022Queue requests/projects in 2021Queue requests/projects in 2020Queue requests/projects in 2019Queue requests/projects in 2018Queue requests/projects in 2017Queue requests/projects in 2016Queue requests/projects in 2015Queue requests/projects in 2014Queue requests/projects in 2013Queue requests/projects in 2012Queue requests/projects in 2011Queue requests/projects in 2010Queue requests/projects in 2009Queue requests/projects in 2008Queue requests/projects in 2007Queue requests/projects in 2006Queue requests/projects in 2005Queue requests/projects in 2004Queue requests/projects in 2003Queue requests/projects in 2002Queue requests/projects in 2001Queue requests/projects in 2000Queue requests/projects in 1999Queue requests/projects in 1998Queue requests/projects in 1997Queue requests/projects in 1996Queue requests/projects in 1995Interconnection.fyi is a free public resource by GridTracker, the research firm behind the interconnection data in LBNL's Queued Up.
© 2026 Interconnection.fyi. All rights reserved.
Deeper asset-level intelligence
Full access via GridTracker
See all the data
Find relevant dockets and filings
Track data center builds