SPP Cluster: Surplus
Total Projects: 126
Active Projects: 89
Active Projects per county
Capacity by Generation Type
Active Projects
Operational Projects
| Queue ID | Status | Capacity (MW) |
|---|---|---|
GEN-2021-SR9 | Operational | 10 |
GEN-2023-SR13 | Operational | 70 |
GEN-2023-SR18 | Operational | 80 |
GEN-2023-SR28 | Operational | 150 |
Withdrawn Projects
| Queue ID | Status | Capacity (MW) |
|---|---|---|
GEN-2020-SR1 | Withdrawn | 40 |
GEN-2020-SR3 | Withdrawn | 200 |
GEN-2020-SR4 | Withdrawn | 150 |
GEN-2021-SR1 | Withdrawn | 81.6 |
GEN-2021-SR2 | Withdrawn | 21.4 |
GEN-2021-SR3 | Withdrawn | 23.4 |
GEN-2021-SR4 | Withdrawn | 22.2 |
GEN-2021-SR5 | Withdrawn | 126 |
GEN-2021-SR6 | Withdrawn | 80 |
GEN-2021-SR7 | Withdrawn | 20 |
GEN-2022-SR1 | Withdrawn | 104.4 |
GEN-2022-SR2 | Withdrawn | 100.8 |
GEN-2022-SR3 | Withdrawn | 100.24 |
GEN-2022-SR4 | Withdrawn | 85 |
GEN-2022-SR5 | Withdrawn | 85 |
GEN-2022-SR6 | Withdrawn | 50 |
GEN-2022-SR7 | Withdrawn | 210 |
GEN-2022-SR8 | Withdrawn | 210 |
GEN-2023-SR10 | Withdrawn | 160 |
GEN-2023-SR11 | Withdrawn | 200 |
GEN-2023-SR14 | Withdrawn | 165 |
GEN-2023-SR15 | Withdrawn | 50 |
GEN-2023-SR17 | Withdrawn | 120 |
GEN-2023-SR2 | Withdrawn | 85 |
GEN-2023-SR21 | Withdrawn | 235 |
GEN-2023-SR23 | Withdrawn | 73.5 |
GEN-2023-SR24 | Withdrawn | 25 |
GEN-2023-SR3 | Withdrawn | 50 |
GEN-2023-SR6 | Withdrawn | 100.24 |
GEN-2024-SR1 | Withdrawn | 84 |
GEN-2024-SR12 | Withdrawn | 20 |
GEN-2024-SR13 | Withdrawn | 52.2 |
GEN-2024-SR4 | Withdrawn | 300 |
Stay up to date via our email newsletter:
Interconnection queue requests/projects in list format
All transmission grid interconnection queue requests/projects All distribution grid (DG) interconnection queue requests/projects Data center projects by state EIA860 planned and operational power plant projectsInsights
Charts State of interconnection queues — January 2024In 2024, interconnection queues shrank for the first time in yearsAll insightsGridTracker
GridTracker — the full interconnection data platformAbout GridTrackerQueue requests/projects by country
Queue requests/projects by power market
Queue requests/projects by status
Queue requests/projects by cluster
Queue requests/projects by U.S. state
Queue requests/projects by Canadian province
Data Centers
All data center projectsBy U.S. State
Interconnection queue requests/projects by transmission owner
Interconnection queue requests/projects by year
Queue requests/projects in 2026Queue requests/projects in 2025Queue requests/projects in 2024Queue requests/projects in 2023Queue requests/projects in 2022Queue requests/projects in 2021Queue requests/projects in 2020Queue requests/projects in 2019Queue requests/projects in 2018Queue requests/projects in 2017Queue requests/projects in 2016Queue requests/projects in 2015Queue requests/projects in 2014Queue requests/projects in 2013Queue requests/projects in 2012Queue requests/projects in 2011Queue requests/projects in 2010Queue requests/projects in 2009Queue requests/projects in 2008Queue requests/projects in 2007Queue requests/projects in 2006Queue requests/projects in 2005Queue requests/projects in 2004Queue requests/projects in 2003Queue requests/projects in 2002Queue requests/projects in 2001Queue requests/projects in 2000Queue requests/projects in 1999Queue requests/projects in 1998Queue requests/projects in 1997Queue requests/projects in 1996Queue requests/projects in 1995Interconnection.fyi is a free public resource by GridTracker, the research firm behind the interconnection data in LBNL's Queued Up.
© 2026 Interconnection.fyi. All rights reserved.
Deeper asset-level intelligence
Full access via GridTracker
See all the data
Find relevant dockets and filings
Track data center builds